In SAP MM and PP as at ECC6.0, which of the following parameters are included in the MRP Group parameters ?
(more then one answers)
A) Planning Horizon.
B) Creation Indicators.
C) Number ranges for Planned Orders.
D) Purchasing Processing time.
E) Start Date in the Past.
.
(more then one answers)
A) Planning Horizon.
B) Creation Indicators.
C) Number ranges for Planned Orders.
D) Purchasing Processing time.
E) Start Date in the Past.
.
Review settings at OPPR.
ReplyDeleteNumber ranges, Purchasing processing time, and Start date in the past parameters are at the Plant Parameter.