This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Friday, August 23, 2013

Question no 2014 : MRP Group Parameters

In SAP MM and PP as at ECC6.0, which of the following parameters are included in the MRP Group parameters ?

(more then one answers)

A)     Planning Horizon.
B)     Creation Indicators.
C)     Number ranges for Planned Orders.
D)     Purchasing Processing time.
E)     Start Date in the Past.
.

2 comments:

  1. Number ranges, Purchasing processing time, and Start date in the past parameters are at the Plant Parameter.

    ReplyDelete