In SAP PP ECC6.0, the Material BOM created is used for which of the following module or purpose ?

(more then one answers)

A)     Product Cost Planning.
B)     Sales Order Entry.
C)     Material Requirement Planning Run.
D)     Production Order Creation.
E)     Subcontracting Purchase Order.
.