Question no 1997 : Planning Horizon

In SAP MM and PP ECC6.0, you can find the Planning Horizon in which of the following ?

(more then one answers)

A)     MRP 2 view of the Material Master.
B)     Plant Parameter.
C)     MRP Profile to be assigned to the Material Master.
D)     MRP Group Parameter.
E)     Factory Calendar assigned to the Plant of the Material Master.

1 comment:

  1. The Planning Horizon can only be found in the Customizing (as at ECC6.0), the system will first check the Planning Horizon at the MRP Group assigned to the Material Master; if not available, it will then check the Planning Horizon at the Plant Parameter.