In SAP PM ECC6.0, when creating a Single-Cycle Plan where the call object is a Maintenance Order, you should have the following data entry.
(more then one answers)
A) At least one technical object
B) Settlement rule at the Header Maintenance Plan
C) At least One Maintenance item
D) One or more Maintenance Task List for each Maintenance item
E) Save the Maintenance Plan with or without cycle start date.
.
(more then one answers)
A) At least one technical object
B) Settlement rule at the Header Maintenance Plan
C) At least One Maintenance item
D) One or more Maintenance Task List for each Maintenance item
E) Save the Maintenance Plan with or without cycle start date.
.
Answer: C, E
ReplyDeleteA) You can create a Single-Cycle with or without a technical object, or more then one technical objects.
ReplyDeleteB) You can create settlement rules for maintenance items that will be copied into the maintenance order on order creation BUT not at the Header of the maintenance plan.
ReplyDeleteC) There must be at least one maintenance item for the maintenance plan of Single-Cycle plan.
ReplyDeleteD) Only one task list for each maintenance item is allowed in the Single-Cycle Plan.
ReplyDeleteE) When saving the maintenance plan, the system will prompt for the cycle-start date, you can also opt to save without the cycle-start date.