In SAP MM ECC6.0, which of the following are NOT TRUE when creating a Source List ?
(only one answer)
A) The Source List Requirement indicator must be selected in the Material Master before Source List for the Material can be created.
B) The Source List Requirement indicator for Plant must be selected in the Customizng before Source List for the Material can be created.
C) When assigning a Vendor to the Source List, the Purchasing Info Record is a pre-requisite.
D) The Source in the Source List cannot be remove from the Source List unless all Purchase Requistions and Purchase Order are deleted or completed.
E) A source list can be created with or without Plant.
.
(only one answer)
A) The Source List Requirement indicator must be selected in the Material Master before Source List for the Material can be created.
B) The Source List Requirement indicator for Plant must be selected in the Customizng before Source List for the Material can be created.
C) When assigning a Vendor to the Source List, the Purchasing Info Record is a pre-requisite.
D) The Source in the Source List cannot be remove from the Source List unless all Purchase Requistions and Purchase Order are deleted or completed.
E) A source list can be created with or without Plant.
.
Answer: A, B, C, D, E
ReplyDeleteA, B) The Source List Requirement indicators are not to control the creating of Source List but to ensure the Source must be in the Source List when the Source is assigned to the Purchasing Document.
ReplyDeleteC) If you do not select an MRP indicator in the Source List, then the Purchasing Info Record is not neceesary when creating a Source List for the Vendor.
ReplyDeleteD) You can remove the Source form the Source List irrespective of whether there are any Purchasing Documents present for the material.
ReplyDeleteE) A Source List is always created at the Plant Level.
ReplyDelete