Question no 1991 : MRP Pre-requisite

In SAP MM or PP ECC6.0, which of the following are per-requisites of MRP run ?

(more then one answers)

A)    A valid MRP type in the MRP 1 view.
B)    A source list.
C)    A purchasing info record.
D)    MRP Plant Parameters.
E)    Activation of MRP Run at Plant level in the Customizing.
.

2 comments:

  1. Both the Source List and Purchasing Info Record are not required for MRP Run to be executed. Source List is desirable when Automatic Source Determination is required at MRP run.