In SAP MM or PP ECC6.0, which of the following are per-requisites of MRP run ?
(more then one answers)
A) A valid MRP type in the MRP 1 view.
B) A source list.
C) A purchasing info record.
D) MRP Plant Parameters.
E) Activation of MRP Run at Plant level in the Customizing.
.
(more then one answers)
A) A valid MRP type in the MRP 1 view.
B) A source list.
C) A purchasing info record.
D) MRP Plant Parameters.
E) Activation of MRP Run at Plant level in the Customizing.
.
Answer: B, C
ReplyDeleteBoth the Source List and Purchasing Info Record are not required for MRP Run to be executed. Source List is desirable when Automatic Source Determination is required at MRP run.
ReplyDelete