This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Monday, October 3, 2016

Question no 3296 : Production Order creation

In SAP PP as at ECC6.0 EhP6, a Production Order can be created with which of the following options ?

(more than one answers)

A)  Without Material.
B)  Without Routing.
C)  Without Plant.
D)  Without BOM.
E)  Without a Work Center.
.

1 comment:

  1. Answer: A, B, D, E

    A, D) CO07 create Production Order without Material, hence BOM also not required.
    B) Production Order must be created with an Operation (not necessary a Routing).
    C) Plant is mandatory for Production Order creation.

    ReplyDelete