Question no 3293 : Material Master view for PP

In SAP PP as at ECC6.0 EhP6, which of the following data view in the Material Master contain the following information ?

. BOM and Routing
. Goods Issue and Goods Receipt Storage Location.
. Production Line.

(only one answer)

A)  MRP 3 data view.
B)  Work Scheduling data view.
C)  Production Version additional data view.
D)  MRP2 data view.
E)  Non of the above.
.