In SAP PP as at ECC6.0 EhP6, the PP Routing can be used for which of the following ?
(more than one answers)
A) Costing.
B) MRP.
C) Capacity Calculation.
D) Long Term Planning.
E) SOP Planning.
.
(more than one answers)
A) Costing.
B) MRP.
C) Capacity Calculation.
D) Long Term Planning.
E) SOP Planning.
.
Answer: A, B, C, D
ReplyDeleteExcept SOP which uses Rough Cut Capacity Profile for capacity calculaton.