Question no 3299 : Project System Structure Assignments

In SAP PS as at ECC6.0 EhP6, which of the following assignments in PS are correct ?

(more than one answers)

A)  more than one network structure can be assign to one Operative Project.
B)  one of more network activities can be assign to a WBS.
C)  activities from more than one network structure an be assign to a WBS.
D)  a project cannot be saved without a network structure.
E)  one or more project definition can exist in a Project structure.
.

1 comment:

  1. Answer: A, B, C

    D) A project can be created with only WBS if detail scheduling and capacity is not required.