In SAP PS as at ECC6.0 EhP6, which of the following assignments in PS are correct ?
(more than one answers)
A) more than one network structure can be assign to one Operative Project.
B) one of more network activities can be assign to a WBS.
C) activities from more than one network structure an be assign to a WBS.
D) a project cannot be saved without a network structure.
E) one or more project definition can exist in a Project structure.
.
(more than one answers)
A) more than one network structure can be assign to one Operative Project.
B) one of more network activities can be assign to a WBS.
C) activities from more than one network structure an be assign to a WBS.
D) a project cannot be saved without a network structure.
E) one or more project definition can exist in a Project structure.
.
Answer: A, B, C
ReplyDeleteD) A project can be created with only WBS if detail scheduling and capacity is not required.