In SAP PP as at ECC6.0 EhP6, the Collective Production Order scenario can be set via which of the following ?
(more than one answers)
A) Special Procurement key in the Material Master MRP 2 data view.
B) Item Category in the Bill of Material.
C) BOM Item detail.
D) BOM Header.
E) Routing Operation details Control Key.
.
(more than one answers)
A) Special Procurement key in the Material Master MRP 2 data view.
B) Item Category in the Bill of Material.
C) BOM Item detail.
D) BOM Header.
E) Routing Operation details Control Key.
.
Answer: A, C
ReplyDeleteThe Special Procurement key provides the feature in both Material master MRP 2 view and BOM item detail.