In SAP PP as at ECC6.0 EhP6,
Working time of a work center is 0700 to 1630 hrs, break time is 1.5 hours with overload 110%. Capacity utilization 80%, no of machines is 2. What is the available capacity?
(only one answer)
A) 12.8 hours
B) 12.0 hours
C) 14.08 hours
D) 15 hours
E) 17.6 hours
.
Working time of a work center is 0700 to 1630 hrs, break time is 1.5 hours with overload 110%. Capacity utilization 80%, no of machines is 2. What is the available capacity?
(only one answer)
A) 12.8 hours
B) 12.0 hours
C) 14.08 hours
D) 15 hours
E) 17.6 hours
.
Answer: A
ReplyDelete((16.5 - 7) - 1.5) x 80/100 x 2 = 12.8