In SAP MM as at ECC6.0 EhP6, when using Re-Order Point Planning, which of the following are mandatory entries in the MRP1 and MRP 2 data view in the Material Master ?
(more than one answers)
A) Safety Stock.
B) Re-Order level.
C) Lot Size key.
D) Fixed Lot size.
E) Rouding.
.
(more than one answers)
A) Safety Stock.
B) Re-Order level.
C) Lot Size key.
D) Fixed Lot size.
E) Rouding.
.
Answer: B, C
ReplyDeleteBasically, regardless of MRP type (valid MRP type for MRP planning), the Lot size key, Procurement type, SMK, external lead time are mandatory by system delivery. However, ROP MRP type VB would require the Re-Order level to be entered. Safety stock is always optional.