Question no 3274 : Interoperation times in PP

In SAP PP as at ECC6.0 EhP6, which of the following are Inter-operation times ?

(more than one answers)

A)  Queue time.
B)  Setup time.
C)  Teardown time.
D)  Wait time.
E)   Move time.
.

1 comment:

  1. Answer: A, D, E

    Queue time + Wait time + Move time = Inter-operation times

    ReplyDelete