In SAP PM ECC6 EhP6, the maintenance order can be closed (business closing 'CLSD') when _______________ .
(only one answer)
A) All Purchase Order refernce to the Order is completed.
B) All Invoice for PO for Order is completed.
C) All User Staus are checked.
D) All Materials are issued.
E) All Costs are settled and no remainng costs in the Order.
.
(only one answer)
A) All Purchase Order refernce to the Order is completed.
B) All Invoice for PO for Order is completed.
C) All User Staus are checked.
D) All Materials are issued.
E) All Costs are settled and no remainng costs in the Order.
.
Answer: E
ReplyDeleteWhen costs in MO is zerorized then the MO can set with business closing status, all other answers are not valid.