In LE-WMS as at ECC6.0 EhP6, the following configuration parameter for Production Scheduling Profile for staging material to a Production Order from a WMS environment, in this case transfer requirement will be generated for which types of material when the Production Order is Release ?
(only one answer)
A) Release Order Parts only.
B) Crate Parts only.
C) Pick Parts only.
D) Pick Parts and Release Order Parts.
E) Pick Parts, Release Order Parts, and Crate Parts.
.
(only one answer)
A) Release Order Parts only.
B) Crate Parts only.
C) Pick Parts only.
D) Pick Parts and Release Order Parts.
E) Pick Parts, Release Order Parts, and Crate Parts.
.
Answer: C
ReplyDeleteOnly Pick List items which is in the control cycle of staging indicator 1 will be created into the Transfer Requirement when the Production Order is Release. Other staging methods such as Release Order Part or Crate Part are staging using t-code LP12 and LP11 respectively.