In SAP LE-WMS as at ECC6.0 EhP6, which of following staging methods where the staging of quantities of the production supply area are independent of the production order quantities ?

(only one answer)

A)   Pick list item.
B)   Pick list item and Crate Parts.
C)   Create Parts.
D)   Release Order Parts.
E)   Pick list and Release Order Parts.

2 comments:

  1. If you check the control cycle of Crate Parts, it is with Kanban Container and therefore its replenishment is based on container quantity.

    While Release Order Parts and Pick List item control cycle are without Kanban Containers and their replenishment is directly influenced by the Production Order quantities.