In SAP PM/CS ECC6 EhP6, which of the following object in Plant Maintenance or Customer Service is used directly to derive the Cost Element for operation cost presentation in Maintnenance/Service Order ?
(only one answer)
A) Cost Center.
B) Costing Variant.
C) Work Center.
D) Control Key.
E) Activity Type.
.
(only one answer)
A) Cost Center.
B) Costing Variant.
C) Work Center.
D) Control Key.
E) Activity Type.
.
Answer: E