In SAP for MRP planning as at ECC6.0 EhP6, which of the following parameters are NOT possible at the MRP area level in the Material Master ?
(more than one answers)
A) Strategy Group.
B) Special Procurement type.
C) Procurement type.
D) GR processing time.
E) Planned delivery time.
.
(more than one answers)
A) Strategy Group.
B) Special Procurement type.
C) Procurement type.
D) GR processing time.
E) Planned delivery time.
.
Answer: A, C, D
ReplyDeleteA) Strategy Group is at the MRP 3 view at the Plant level only. (MRP area only contains MRP1, 2 views)
ReplyDeleteB, C) The Procurement type (external or in-house) is at the Plant level MRP 2 view only. However Special Procurement type can be at both Plant and MRP area level.
ReplyDeleteD, E) GR Processing time only at Plant level but Planned delivery time can be at MRP area and Plant level.