Question no 2943 : Estimated Costs in Maintenance Order

In SAP PM ECC6 EhP6, which ofmthe following statements are correct about Estimates Costs in the Maintenance Order ?

(more than one answers)

A)  Costing Variant has no influence on deriving the estimated costs.
B)  Estimated Costs are locked out for maintenance once the Order is released.
C)  When Actual Costs exceeds the Estimated Costs at the time of posting, the system issues a Warning Message.
D)  Presentation Of Estimated Costs are entered as Value Categories.
E)  Estimated Costs can be found in PMIS and List Display reports.
.

2 comments:

  1. Estimated Costs can be entered before Order release and it is passive data for information purpose only. (as at ECC6 EhP6)