This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Friday, April 3, 2015

Question no 2925 : Inspection Container in Result Recording for Equipment Calibration

In SAP PM/CS ECC6.0 EhP6, which of the following parameter ensures Equipments registered within a Calibration Maintenance Plan; when performing resulting recording, the system provides containers for recording results of calibration for each of the Equipment registered ?

(only one answer)

A)  Inspection Point assign to the Inspection Origin.
B)  Inspection Point assign to the Inspection Type.
C)  Inspection Point assign to the Task List header.
D)  Inspection Point assign to the Functional Location Master.
E)  Inspection Point assign to the Equipment Master.
.

1 comment:

  1. IA05 or IA06 check task list header and locate inspection point. This parameter allows inspection of several equipments within an inspection lot.

    ReplyDelete

Note: Only a member of this blog may post a comment.