In SAP PM as at ECC6.0 EhP6, what are the methods where Maintenance Order can be creared ?
(more than one answers)
A) Creation of Maintenance Notification.
B) Maintenance Event Builder.
C) Maintenance Plan Scheduling.
D) Graphical Resource Planning in Pool Asset Management.
E) Overall Confirmation.
.
(more than one answers)
A) Creation of Maintenance Notification.
B) Maintenance Event Builder.
C) Maintenance Plan Scheduling.
D) Graphical Resource Planning in Pool Asset Management.
E) Overall Confirmation.
.
Answer: A, B, C, D
ReplyDeleteD) When completing a Tool demand request (Notification) in Graphical Resource Planning in PAM, the system generates Maintenance Order to collect the Tool rental/usage costs)
ReplyDelete