In SAP PM/CS as at ECC6 EhP6, what does the Response Profile do in a Maintenance/Service Order ?
(only one answer)
A) Default the Priority.
B) Time sceduling parameter for each Priority.
C) Activity and Task code default.
D) Priority dependent Task codes default.
E) Notorication type dependent Task and Activity code default.
.
(only one answer)
A) Default the Priority.
B) Time sceduling parameter for each Priority.
C) Activity and Task code default.
D) Priority dependent Task codes default.
E) Notorication type dependent Task and Activity code default.
.
Answer: D