In SAP PM, which of the following preventive maintenance scenario require a maintenance strategy when creating the maintenance plan ?
(more than one answers)
A) Single cycle plan, time-based.
B) Single cycle plan, performance-based.
C) Strategy plan, time-based.
D) Strategy plan, performance-based.
E) Multiple counter plan.
.
(more than one answers)
A) Single cycle plan, time-based.
B) Single cycle plan, performance-based.
C) Strategy plan, time-based.
D) Strategy plan, performance-based.
E) Multiple counter plan.
.
A, B) Single Cycle plans do not need a strategy as the cycle is fixed either by time (for example every 3 months) or counter (every 5000 hours), all operations from the tasks list should be executed.
ReplyDeleteC, D) Strategy Plan (multi cycle) of both time and performance (counter) will require a strategy to lock in the multi cycle logic matching the operations required in the task list. Therefore, they require a Strategy.
ReplyDeleteE) Multi counter plan uses a different logic which is a master object called the Cycle Set which contains the multiple unit of measure. The Cycle Set is not assigned to the task list and it is not related to a Strategy Plan.