Question no 2674 : Strategy Plan in SAP Plant Maintenance

In SAP PM, which of the following preventive maintenance scenario require a maintenance strategy when creating the maintenance plan ?

(more than one answers)

A)   Single cycle plan, time-based.
B)   Single cycle plan, performance-based.
C)   Strategy plan, time-based.
D)   Strategy plan, performance-based.
E)    Multiple counter plan.

3 comments:

  1. A, B) Single Cycle plans do not need a strategy as the cycle is fixed either by time (for example every 3 months) or counter (every 5000 hours), all operations from the tasks list should be executed.

    ReplyDelete
  2. C, D) Strategy Plan (multi cycle) of both time and performance (counter) will require a strategy to lock in the multi cycle logic matching the operations required in the task list. Therefore, they require a Strategy.

    ReplyDelete
  3. E) Multi counter plan uses a different logic which is a master object called the Cycle Set which contains the multiple unit of measure. The Cycle Set is not assigned to the task list and it is not related to a Strategy Plan.