In SAP Plant Maintenance as at ECC6.0 EhP5, the maintenance engineer wishes maintenance order to be due every 30 days on the 15th day of the month, which of the following scheduling indicator would you recommend ?
(only one answer)
A) Time-based.
B) Time-based with key date.
C) Time-based with factory calendar.
D) Day-based with key date.
E) Day-based with factory calendar.
.
(only one answer)
A) Time-based.
B) Time-based with key date.
C) Time-based with factory calendar.
D) Day-based with key date.
E) Day-based with factory calendar.
.
Time-based with key date would be the choice.