Question no 3217 : Long Term Planning Scenario parameters

In SAP PP as at ECC6.0 EhP7, which of the following Parameters can be set in a Long Term Planning Scenario ?

(more than one answers)

A)   Switch off scrap calculations.
B)   Use a different scarp %.
C)   Consider Production Orders, Purchase Orders, and Sales Orders.
D)   Consider Planned Orders.
E)   Set a time fence.
.

2 comments:

  1. A, B) You can switch off scrap factors but not assign a different scarp %.
    C, D) You can decided to Consider on Ignore Sales Order, You can decide to include Firm Receipts which are Manually created PRs, POs, Delivery Schedules, Repetitive Planned Orders, Production Orders, and Process Orders.
    E) You can switch off time fence but not set a different time fence.