In SAP PP or MM as at ECC6.0 EhP7, which of the following MRP element cannot be displayed as Supplu element in the Stock Requirements List ?
(More than one answers)
A) Purchase Requisition.
B) Request for Quotation.
C) Purchase Order.
D) Contract.
E) Delivery Schedules for Scheduling Agreements.
.
(More than one answers)
A) Purchase Requisition.
B) Request for Quotation.
C) Purchase Order.
D) Contract.
E) Delivery Schedules for Scheduling Agreements.
.
Answer: B, D
ReplyDeleteContract, Scheduling Agreement and RFQ/Quotation are not published in the S/R List, however Delivery Schedules for Scheduling Agreement can be seen in MD04.
ReplyDelete