In SAP PP or MM MRP, as at ECC6.0 EhP6, based on the following Stock Requirement List, deduce what was the parameter which resulted in the MRP result ?
(more than one answers)
A) Takt time.
B) Fixed lot size.
C) Maximum stock level.
D) Rounding value.
E) Minimum lot size.
.
Answer: A, B
ReplyDeleteYou can see that the system calculates 75 for each PR, this should be due to the Fixed Lot size of 50, and the dates are forward 1 day for each PR which is due to the Takt time of 1.