Question no 3220 : Deduce a Lot Size calculation parameters

In SAP PP or MM MRP, as at ECC6.0 EhP6, based on the following Stock Requirement List, deduce what was the parameter which resulted in the MRP result ?

(more than one answers)


A)  Takt time.
B)   Fixed lot size.
C)   Maximum stock level.
D)   Rounding value.
E)   Minimum lot size.
.

2 comments:

  1. You can see that the system calculates 75 for each PR, this should be due to the Fixed Lot size of 50, and the dates are forward 1 day for each PR which is due to the Takt time of 1.