Question no 3203 : Planned Independent Requirements

In SAP PP Planning as at ECC6.0 EhP7, which of the following statements are TRUE about Planned Independent Requirements EXCEPT one ?

(only one answer)

A)   It is presented in the S/R list as the Demand.
B)   After saving a PIR, it will only appear in the S/R list after an MRP run.
C)   A PIR must have a Requirement Type.
D)   A PIR can be generated and transferred from SOP or Demand Planning.
E)   Quantities from a PIR can be reduced by a Sales Order delivery.
.