In SAP PP Planning as at ECC6.0 EhP7, how can you ignore stocks during MRP planning for a material ?
(more than one answer)
A) Gross Planning indicator in the MRP Strategy's Planned Independent Requirement Type.
B) Gross Planning indicator in the MRP Strategy's Customer Requirement Type.
C) Mixed MRP indicator "2" in the Material Master MRP 3 data view.
D) Mixed MRP indicator "2" in the MRP Type configuration assigned to Material in MRP 1 data view.
E) Gross Planning indicator in the MRP Type configuration assigned to Material in MRP 1 data view.
.
Answer: A, C
ReplyDeleteConsider Strategy 11 where the Requirement type BSF is configure with Planning Indicator for Gross Planning PLUS setup a Mixed MRP indicator = 2 in the Material Master MRP 3 data view.
ReplyDelete