This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Thursday, March 5, 2015

Question no 2672 : Maintenance Order and Commitment Accounting

In SAP PM, which of the following in the Maintenance Order creates a commitment accounting posting and tracking ?

(more than one answers)

A)  enter a component with item category 'L'.
B)  enter a component with item category 'N'.
C)  enter  an operation with control key 'PM01'.
D)  enter  an operation with control key 'PM02'.
E)  enter  an operation with control key 'PM03'.
.

1 comment:

  1. Because B, D, E creates a purchase requisition, and only external procurement as such creates commitment accounting.

    ReplyDelete