This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Sunday, March 31, 2013

Question no 1868 : MRP Run Planned Order Conversion

In SAP MM and PP ECC6.0, the planner reviewed the planned order of 1000 pieces and decide to convert only 600 into purchase requisition, what is the systems normal response ?

(only one answer)

(A)   It saved the purchase requisition of 600 pcs and creates 400 for a new planned order.
(B)   It saved the purchase requisition of 600 pcs and a remainder of 400 in the original planned order.
(C)   It saved the purchase requisition of 600 pcs and deletes the original planned order, the remaining 400 is void as the planner decide only to convert 600 of the 1000 pcs.
(D)   It saved the purchase requisition of 600 pcs and prompts a warning message to delete or retain the remaining 400 pcs.
(E)   It saved the purchase requisition of 600 pcs and creates an exception message of the remaining 400 pcs.

1 comment:

  1. The remaining quantities remains in the Planned Order after conversion.

    ReplyDelete

Note: Only a member of this blog may post a comment.