This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Tuesday, March 19, 2013

Question no 1855 : Requirement date

In SAP MM or PP ECC6.0, for a weekly forecast, the requirements date would be set on the first work day of the week because:

(only one answer)

(A)  It is hard coded within the SAP system
(B)  It is a traditional planning technique and algorithm
(C)  It is assumed that total requirement must be available at the beginning of the period.
(D)  It is due to planning accuracy requirements
(E)  It is most convenient and efficient for MRP runtime calculation.

2 comments:

  1. It is normally assumed that the requirement for a demand is to be fulfilled at the first work day of the planning period. However, SAP provides additional fine tuning parameters for requirement date calculations besides the first work day.

    ReplyDelete

Note: Only a member of this blog may post a comment.