In SAP MM ECC6.0 EhP4.0, which of the statements are TRUE about the use of Material Status for the Material Master ?
(more then one answers)
A) It can be entered in the material master without a valid date.
B) The cross-plant material status has higher priority over the plant-specific material status.
C) The material status can be remove any time from the material master.
D) A material status configured in the customizing can be used for cross-plant or plant-specific.
E) Once a material status is assigned to the material master, all stocks and on-order quantities must be cleared before the material status can be remove from the material master.
.
(more then one answers)
A) It can be entered in the material master without a valid date.
B) The cross-plant material status has higher priority over the plant-specific material status.
C) The material status can be remove any time from the material master.
D) A material status configured in the customizing can be used for cross-plant or plant-specific.
E) Once a material status is assigned to the material master, all stocks and on-order quantities must be cleared before the material status can be remove from the material master.
.
Answer: A, B, C, D
ReplyDeleteThe use of material status is quite flexible and there are no difference between the cross-plant or plant-specific material status except the cross-plant setup has a higher priority over the plant-specific setup. It can be remove from the material master anytime.
ReplyDelete