In SAP MM and PP ECC6.0, which of the following activities will lead to the planning file being marked for the next planning run ?
(more than one answers)
(A) Excessive scrap reported which was not planned.
(B) New sales order entered.
(C) When dates for the purchase order has been changed.
(D) Deleting or set deletion flag for a reservation created earlier.
(E) Changing certain MRP parameter fields in the Material master.
.
(more than one answers)
(A) Excessive scrap reported which was not planned.
(B) New sales order entered.
(C) When dates for the purchase order has been changed.
(D) Deleting or set deletion flag for a reservation created earlier.
(E) Changing certain MRP parameter fields in the Material master.
.
Answer: A, B, C, D, E
ReplyDeleteThere are many conditions of which the planning file entry may be flagged or marked to indicate supply is no longer balance with demand. The above are just a few.
ReplyDelete