In SAP MM and PP ECC6.0, the following are true about the various types of planning run ?
(more than one answers)
(A) Re-generative MRP planning run is only possible in the Total planning mode.
(B) Net change planning (NETCH) indicator is flagged when planning changes occur within the planning horizon only.
(C) Net change planning in the planning horizon (NETPL) indicator is flagged when planning changes occur outside the planning horizon.
(D) The planning file of a material can have either NETCH or NETPL being flagged but not both.
(E) When NETPL is flagged, usually the NETCH will also be flagged when planning changes occur within the planning horizon.
.
(more than one answers)
(A) Re-generative MRP planning run is only possible in the Total planning mode.
(B) Net change planning (NETCH) indicator is flagged when planning changes occur within the planning horizon only.
(C) Net change planning in the planning horizon (NETPL) indicator is flagged when planning changes occur outside the planning horizon.
(D) The planning file of a material can have either NETCH or NETPL being flagged but not both.
(E) When NETPL is flagged, usually the NETCH will also be flagged when planning changes occur within the planning horizon.
.
Answer: A, E
ReplyDeleteNETCH is (Net Change) which means any changes results in demand or supply not balance is indicator of a need for planning and therefore this indicator is flagged.
ReplyDeleteNETPL is (Net Change within Planning Horizon) is similar to NETCH in terms of principles but it is for situation within the Planning Horizon.
NEUPL is (Regenerative MRP) is only for Total MRP Run example using MD01.