Question no 1663: PP Work centers

In SAP ECC6.0 PP, which of the following statements are true about PP work centers ?

(more then one answers)

A)    More then one PP work center can be assigned to one cost center.
B)    The formulas for capacity calculation and scheduling need to be the same.
C)    More then one capacity categories are allowed for each PP work center.
D)    Implementing shift sequence in a PP work center is optional.
E)    A PP work center must use the same factory calendar from the Plant the work center is created.
.

6 comments:

  1. A) SAP allows one to many relationship between cost center and the PP work center.

    ReplyDelete
  2. B) It may not be advisable to use a different formula for the capacity calculation and scheduling calculation but assigning a different formula is possible.

    ReplyDelete
  3. C) The usual capacity category for a machine operated by humans are Machine Capacity Category and Labor Capacity Category. However, for a fully automated machine, it may have just the Machine Capacity Category. The assignment of capacity category to the work center is not dictated by the SAP system, it is depending on the characteristics of the Production Work Center.

    ReplyDelete
  4. D) Shift sequence setup in each Capacity Category is always optional.

    ReplyDelete
  5. E) With the Capacity Category's detail or Header Capacity Screen, you can assign a different Factory Calendar then the Plant Calendar.

    ReplyDelete