In SAP ECC6.0, the Bill of Material can be created in the following manners except ?
(more then one answers)
A) create a BOM without material and assign to several materials.
B) create a BOM without plant and assign to several plants.
C) create a BOM for a material group with inclusion indicator.
D) create a BOM without material and plant, then assign to several materials and several plants.
E) create a BOM as a Variant BOM of other materials.
.
(more then one answers)
A) create a BOM without material and assign to several materials.
B) create a BOM without plant and assign to several plants.
C) create a BOM for a material group with inclusion indicator.
D) create a BOM without material and plant, then assign to several materials and several plants.
E) create a BOM as a Variant BOM of other materials.
.
As an ECC6, creating a BOM and then assign to several material is not yet possible. However, you can create a BOM without Plant and later assign it to several Plant (it is called a Group BOM)
ReplyDeleteThere is also another type of BOM Group called Variant BOM. A material BOM can be assiged to technical type called "Variant BOM" where several assemblies of finished goods can share the same Variant BOM. It is especially useful for assemblies/FG that contains many common material components.
ReplyDelete