In SAP as at ECC6.0, if you create a BOM without reference to a Plant in PP, it is called a ________ .
(only one answer)
A) Simple BOM.
B) Material-less BOM.
C) Non-plant BOM.
D) Group BOM.
E) Plant-less BOM.
.
(only one answer)
A) Simple BOM.
B) Material-less BOM.
C) Non-plant BOM.
D) Group BOM.
E) Plant-less BOM.
.
Answer: D
ReplyDeleteYou can create a Group BOM by no entering a Plant using t-code CS01, you then assign the Group BOM to multiple plants using t-code CS07; after that, the maintenance of the Group BOM can be done using t-code CS05.
ReplyDelete