Question no 1659: What PP Strategy

In SAP PP, which of the following PP strategies allow MRP run to recognize the Planned Independent Requirements ?

(more then one answers)

A)   Strategy 10.
B)   Strategy 20.
C)   Strategy 30.
D)   Strategy 40.
E)   Strategy 50.
.

2 comments:

  1. Strategy 10, 30, 40 are all Make to Stock Strategy and the Planned Independent Requirements are recognized at MRP run. However, Strategy 20 and 50 are both Make to Order Strategy; but there are no requirement type on the demand side for Strategy 20 and therefore Planned Independent Requirements are not recognized at MRP run. Strategy 50 is quite different as the Planned Independent Requirements are recognized at MRP run so that components can be ordered before the Sales Order for the Finish Goods arrives.