In SAP PM as at ECC6.0 EhP6, which of the following condition in the Maintenance Order creates a Purchase Requisition item ?
(more than one answers)
A) Operation Control Key "PM01".
B) Operation Control Key "PM02".
C) Operation Control Key "PM03".
D) Operation Control Key "PM04".
E) Operation Control Key "PM05".
.
(more than one answers)
A) Operation Control Key "PM01".
B) Operation Control Key "PM02".
C) Operation Control Key "PM03".
D) Operation Control Key "PM04".
E) Operation Control Key "PM05".
.
Answer: B, C
ReplyDeleteB) is External Operation and C) is External Services both result in PR items.