In SAP PM as at ECC6.0 EhP6, the following processes are possible for both Equipment and Functional Location EXCEPT ?

(only one answer)

A)   Assigned to a Construction Type.
B)   Subjected to Calibration.
C)   SAP Subcontracting Process via Split Valuations.
D)   Performance-Based Maintenance Plan.
E)   Link to an Asset Master.
.

1 comment:

  1. Answer: C

    As Functional Location cannot be linked to Material-Serial Number, therefore SAP Subcontracting Processing via MM Split Valuations is not possible.