Question no 3369 : Inter-operation time elements in Routing

In SAP PP as at ECC6.0 EhP6, which of the following are Inter-operation time elements in SAP PP Routing ?

(more than one answers)

A)   Setup time.
B)   Processing time.
C)   Queue time.
D)   Move time.
E)   Wait time.
.

1 comment:

  1. Answer: C, D, E

    Queue, Move, Wait times are classified as Inter-operation times between operations.