Question no 3362 : Bill of Material for Plant Maintenance

In SAP PM as at ECC6.0 EhP6, the validation for Bill of Material created for use in Plant Maintenance is determine by which of the following ?

(only one answer)

A)   BOM Category.
B)   BOM Alternative.
C)   BOM Usage.
D)   Material Type for Material in the BOM Header.
E)   Item Category of each Material in the BOM item level.
.

1 comment:

  1. Answer: C

    The BOM Usage is "4" in standard SAP for Plant maintenance.