In SAP PM as at ECC6.0 EhP6, Commitment Accounting in SAP PM is activated via which of the following ?
(only one answer)
A) Order Type and Planning Plant parameter.
B) Order Type Plant independent parameter.
C) Order Type, Planner Group and Planning Plant parameter.
D) Order Type, Maintenance Activity Type, and Planning Plant parameter.
E) Order Type and Maintenance Plant parameter.
.
(only one answer)
A) Order Type and Planning Plant parameter.
B) Order Type Plant independent parameter.
C) Order Type, Planner Group and Planning Plant parameter.
D) Order Type, Maintenance Activity Type, and Planning Plant parameter.
E) Order Type and Maintenance Plant parameter.
.
Answer: B
ReplyDeleteOrder Type Plant Independent Parameter.