Question no 3366 : Valid for MRP

In SAP MM or PP as at ECC6.0 EhP6, which of the following are pre-requisites for MRP run ?

(more than one answers)

A)   MRP Area.
B)   Plant activated for MRP run.
C)   Valid MRP Type.
D)   Material master Accounting data view.
E)   Planning File Entry for the Material.
.

2 comments:

  1. Answer: B, C, E

    A) MRP Area is optional
    B) The Plant must be activated for MRP run in the IMG.
    C, E) A valid MRP type in the MRP1 data view in the material master will generate a Planning File Entry for the Material.
    D) Material Master Accounting view is not necessary, as "UNBW" can also be planned with a minimum of Purchasing and MRP data view.

    ReplyDelete
  2. Answer: B, C, E

    A) MRP Area is optional
    B) The Plant must be activated for MRP run in the IMG.
    C, E) A valid MRP type in the MRP1 data view in the material master will generate a Planning File Entry for the Material.
    D) Material Master Accounting view is not necessary, as "UNBW" can also be planned with a minimum of Purchasing and MRP data view.