In SAP MM or PP Planning as at ECC6.0 EhP6, which of the following are per-requisites for MRP Run ?
(more than one answers)
A) A valid MRP type in the Material Master.
B) A valid Material status in the Material Master.
C) Plant parameter was created.
D) Plant was activated for MRP run.
E) MRP Area was activated for MRP run.
.
(more than one answers)
A) A valid MRP type in the Material Master.
B) A valid Material status in the Material Master.
C) Plant parameter was created.
D) Plant was activated for MRP run.
E) MRP Area was activated for MRP run.
.
MRP area is optional.