In SAP PM as at ECC6.0 EhP6, which of the following are possible reference objects in the Maintenance Plan Items ?

(more than one answers)

A)   Functional Location, Equipment and Assembly.
B)   Equipment and Assembly.
C)   Without reference objects.
D)   Functional Location only.
E)   Material only.
.

2 comments:

  1. You find the configuration at IMG - PM/CS - Maint.Plan, Work Centers ... - Maintenance Plans - Set Maintenance Plan Categories. In this configuration, assigned to each Maintenance Plan Category is a Reference Object Key provided by SAP, the combinations are delivered by SAP. Go to the config and have a look at the possible combinations.