This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Friday, August 31, 2012

Question no 1657: PP Strategy

In SAP ECC6.0 PP, a customer requires the planning for their major customers using sales order as the volumes are very high and the orders comes early with sufficient time for planning while they are also requirements to plan for warehouse sales to the public using planned independent requirements, which of the following strategy would you recommend ?

(only one answer)

A)    Strategy 10.
B)    Strategy 20.
C)    Strategy 30.
D)    Strategy 40.
E)    Strategy 50.
.

2 comments:

  1. Strategy 30 was delivered by SAP for exactly that purpose. Customer Sales Order will not consume the Planned Independent Requirements; therefore, MRP run will plan the quantity for production for the total of the Sales Orders PLUS the Planned Independent Requirements. Usually, a Periodic Lot Sizing Rule is used for thr Net Requirement determination. Warehouse Sales will be used to reduced the Planned Independent Requirements. This strategy is created as a Make to Stock strategy. While Selling/Delivering Stocks for Sales Orders for the Major Customers only reduces the stock quantity and does not reduce the Planned Independent Requirements. (this is due to the setup of the Requirement Types in Strategy 30)

    ReplyDelete

Note: Only a member of this blog may post a comment.