In SAP PM ECC6.0, which of the following is true about cost management for maintenance operations in maintenance order ?

(only one answer)

A)   The Control Key assign to the Maintenance Operation determine the costing relevancy of the operations.
B)   The user cannot influence the costing relevancy indicator from the Control Key in the Maintenance Order.
C)   The costing relevancy indicator for maintenance order operation is influenced by the Costing Variant assigned to the Order. 
D)   The costing relevancy indicator in the Control Key can only be changed before the Maintenance Order is released.
E)   The costing relevancy for Maintenance Operations is influenced by the Account Assignment of the Technical Object copied into the Maintenance Order.

1 comment:

  1. A, B) The Control Key stores various parameters including the Costing Relevancy indicator; However, the indicator cannot be influenced at the application level.

    ReplyDelete